THE VISION

321 North has a well-considered mix of business, residential and lifestyle components: office, retail and residential, plus the benefits of a full-service hotel. The completed project in Plantation, Florida, will keep local residents spending in the city and encourage people in central Broward County to come for shopping, dining and entertainment.

Companies operating at 321 North will employ people in office, retail, restaurant, residential and other sectors and provide strong support to the local economy.

The innovative design calls for redesigning the interior of the former Fashion Mall and reorienting the stores and restaurants toward North University Drive. This will make the three main levels more visually accessible. Pick-up and drop-off plazas and classic urban gathering spaces will be combined to create a vibrant and convenient lifestyle environment.

321 North will be constructed in five phases, many of which overlap. The master plan calls for an estimated:

  • 500,000 square feet of retail and restaurant space
  • 160,000 square feet of office space
  • 590 condominium-style residential units
  • 264 hotel guest rooms and 5,700 square feet of hotel meeting space
  • 5,000 parking spaces

TIMELINE

321 North is projected to be completed by the end of 2017. Here is the current construction schedule:

First "Stage" of the redevelopment plan puts back into service an existing 7-story office building which is currently under renovation.

Refurbishment of Existing Office Tower I Building
Renovation began: Q1 2014
Renovation complete: Q3 2014
Tenant move-in starts: Q1 2015

Phase I

12-Story North Residential Tower
Construction starts: Q2 2015
Construction complete: Q4 2016

Phase II

North Retail
Renovation begins: Q2 2015
Renovation complete: Q1 2017
First Retail Tenants Open: Q2 2017
Grand Opening: Q4 2017

Phase III

South Retail Wing
Construction starts: Q2 2016
Construction complete: Q4 2017

Phase IV

Central Plaza Retail
Construction starts: Q4 2016
Construction complete: Q2 2018

Phase V

12-story South Residential Tower
Construction starts: Q2 2017
Construction complete: Q4 2018


Developer proposes seeking certification of all or portions of the 321 North project under the LEED® Green Building Rating System™. While Developer aspires to develop portions of the project to ultimately obtain LEED® certification, project certification is only granted after substantial completion and may or not be awarded. Accordingly, Developer does not make any assurances, guarantees, representations, or warranties, express or implied, and specifically disclaims all warranties or representations, that the Developer will pursue, or the project will receive LEED® certification. The information contained herein was obtained from sources believed reliable, however, Developer makes no guarantees, warranties or representations as to the completeness or accuracy thereof. Renderings are artist's concept only. Project specifications, finishes and features are subject to change without notice. Dimensions and square footage are approximate only and are subject to change.